We are working hard on projects across Queen Mary’s UK campuses to increase energy efficiency through smart planning and cutting-edge technologies. Below are three case studies from recent projects implemented in some of our top energy-consuming buildings.
Stage of Works: Completed
Project Details: This involves optimisation works aimed at baseload reduction i.e. making sure that the heating, cooling and air ventilation is meeting temperature set points.
Total kWh saving expected: 100,000
Electric kWh: 65,000
Gas kWh: 35,000
Stage of Works: In progress
Project Details: This involves the installation of meters on 5 MCPs (Mechanical control panels) and connection to 13 Variable Speed Drives.
Total kWh saving expected: 50,000
Electric kWh: 50,000
Gas kWh: 0
Project Details: Networking of 3 Air handling Units.
Total kWh saving expected: 11,255
Electric kWh: 5050
Gas kWh: 6205